SKI SEWER PROJECT UPDATE 12.12.23

Previous (2021) work completed 33 connections

21-01 STEP

On September 15, 2023 the contractor completed phase 2 STEP tank installations and sewer connections to 167 existing homes.     This finalizes the public sewer connections to the 200 existing homes located in Tower Gardens. 

Tracer Wire

Old Septic Tank Abandonment

22-02 Community Mains

On October 20, 2023 the contractor completed phase 3 community mains: pipe work, ARVs, cleanouts and sewer valves to 428 properties.

1