Previous (2021) work completed 33 connections
21-01 STEP
On September 15, 2023 the contractor completed phase 2 STEP tank installations and sewer connections to 167 existing homes. This finalizes the public sewer connections to the 200 existing homes located in Tower Gardens.


Tracer Wire

Old Septic Tank Abandonment
22-02 Community Mains
On October 20, 2023 the contractor completed phase 3 community mains: pipe work, ARVs, cleanouts and sewer valves to 428 properties.