Category: Uncategorized

Project Update 02.23.17

Community Collection LineĀ  Horizontal Directional Drilling (HDD) for the placement of a 3-inch community main will begin on Touhey Drive starting on Thursday, February 23.

Project Update 02.17.2017

STEP Contractor has one more tank to install on Touhey. This tank will be installed on Monday, 02/20/17. The contractor will then move to Margaret Drive to start installing tanks on 02/27/17. The contractor will be using next week to complete restoration on Touhey…

Project Update 02.03.17

STEP 3 pre-construction meetings were held this week and 8 easements were acquired. No tanks were installed this week, will continue to install tanks next week. Contractor has 13 more tanks to install before the end of February. Community Collection Mains Marking out tee…

Project Update 01.27.17

STEP 2 tanks were installed this week. Rain slowed down progress for this week. MDE project signs have been place. Tanks continue to be installed. Community Collection Lines Still waiting on pipe delivery. MDE sign placed. Transmission main will be crossing Maryland and New…

Project Update 01/18/17

STEP Contract Contractor and QAC Staff held 5 Homeowner interviews. Contractor installed 2 STEP tanks. Four tanks scheduled to be installed on Touhey Drive this week. Interviews will be continuing. … Community Collection Lines: Continuing to mark curb stop locations with wooden stakes in…