Category: Uncategorized

SKI Sewer Project Update 10.31.22

Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens.  The contractor continues public sewer utility operations on Beachside Drive.   20 STEP tanks were installed along with the completion… Continue Reading “SKI Sewer Project Update 10.31.22”

SKI Sewer Project Update 8.31.22

22-02 Phase 3 Community Mains For the months of July and August 2022 the contractor has drilled and installed pipe for the community mains in the Kentmorr sub-division. The contractor has moved to Queens Colony High Road to drill and install 6” pipe for… Continue Reading “SKI Sewer Project Update 8.31.22”

SKI Sewer Project Update 8.31.2022

21-01 Phase 2 STEP Previous (2021)  work completed 33 connections. For the month of August 2022  SKI Sewer Project Phase 2 Tower Gardens the contractor installed 15 STEP tanks and completed 13 house connections on North Lake and Beachside Drive, in addition to other… Continue Reading “SKI Sewer Project Update 8.31.2022”

SKI Project update 7.31.22

Previous (2021)  work completed 33 connections. 21-01 STEP For the month of July 2022  SKI Sewer Project Phase 2 Tower Gardens the contractor installed 9 STEP tanks and completed 9 house connections on North Lake Drive. Along with other utility requirements and yard restorations… Continue Reading “SKI Project update 7.31.22”

June 30th, 2022- Southern Kent Island (SKI) Sanitary Project Phase 2

Previous work completed 33 connections on North Lake Drive. 21-01 STEP On May 25th, 2022 – SKI Sewer Project Phase 2 Tower Gardens resumed construction by Cole Ventures, Inc.  to the remaining 168 homes.  Public sewer construction has re-started installing STEP tanks, continuing with… Continue Reading “June 30th, 2022- Southern Kent Island (SKI) Sanitary Project Phase 2”

16-01 STEP

Queen Anne’s County Sanitary District SKI STEP Sewer Service User Information How does my STEP System work? STEP means Septic Tank Effluent Pump.  Your STEP system includes a holding tank for sewage, a screen chamber and a small high-pressure pump within the tank.   The… Continue Reading “16-01 STEP”

SKI Project Update 10.31.21

16-01 STEP Since July the contractor continues to complete yard restorations and submit finalized as- builts to the SKI Community Office. 20-01 STEP June – August the contractor installed 33 STEP Tanks and connected 32 homes to the Public Sewer System.  Tower Gardens sewer… Continue Reading “SKI Project Update 10.31.21”

SKi Project Update 7.31.21

SKI 16-01 STEP For the months of May – July 31st  2021, the contractor installed 39 STEP tanks and completed 82 house connections to the Southern Kent Island Public Sewer System.  There are a few houses that have not been connected to the Public… Continue Reading “SKi Project Update 7.31.21”

SKI Project Update 4.30.21

For the months of March and April 2021, the contractor completed 63 house connections to the Southern Kent Island public sewer system along with septic tank abandonments. Nineteen tanks were installed.  The contractor continues with daily yard stabilization and restoration.  Late spring into early… Continue Reading “SKI Project Update 4.30.21”

SKI Project Update 2.28.21

SKI 16-01 STEP For the months of January and February 2021, the contractor completed 46 house connections to the Southern Kent Island public sewer system; those locations include: Elm Street, Penny Lane, Caroline, Talbot, Tennessee, Wicomico and Worcester Roads.   The contractor worked on finalizing… Continue Reading “SKI Project Update 2.28.21”