Category: Uncategorized

SKI Project Update 4.17.20

STEP For the weeks ending 4/10 and 4/17/2020 the contractor completed 15 house connections to the Southern Kent Island Public Sewer System; those locations were Dorchester, South Carolina, Kent, Cecil and Baltimore Roads.  Four STEP tanks were installed on Dorchester and Baltimore Roads.  The…

SKI Information 04.09.20

The SKI office is currently operating under guidelines from the Governor and Local officials. The construction and inspection aspects of the project are proceeding, while utilizing personal distancing while work is being performed. The office staff are working on a rotating schedule of every…

SKI Project Update 4.3.20

STEP The contractor completed seven house connections to the public sewer system located on Romancoke, Long Point, N. Lake and Dorchester Roads and two STEP tanks were installed on Cecil and Romancoke Roads.  Six electric meter replacements / modifications were installed by the contractor…

SKI Project Update 3.27.20

STEP Two days of rain this week delayed sewer utility progress. The contractor completed six house connections to the public sewer system located on Romancoke, Long Point, South Carolina and Oregon Road and one STEP tank was installed on Dorchester Road. Seven electric meter…

SKI Project Update 3.20.20

STEP This week the contractor completed eight house connections to the public sewer system located on Penny Lane, Oregon, Dorchester and Romancoke Road and four STEP tanks were installed on Romancoke and Oregon Road. Six electric meter replacements / modifications were installed by the…

SKI Project Update 3.13.20

STEP This week the contractor completed eight house connections to the public sewer system located on Penny Lane, Oregon, Long Point and Cecil Road and one STEP tank was installed on Long Point Road. Five electric meter replacements / modifications were installed by the…

SKI Project Update 3.6.20

16-01 STEP This week the contractor completed seven house connections to the public sewer system on Bay Drive, Oregon, Long Point and Utah Road and three STEP tanks were installed on Cecil, Dorchester and Long Point Road. Ten electric meter replacements / modifications were…