Category: Uncategorized

SKI project update 11.15.19

STEP During the first two weeks of November the contractor completed 6 house connections to the Public Sewer System and installed Five STEP tanks on Bay Drive and Queen Anne Road.   The contractor installed 326LF of 4” gravity sewer line to those individual homes…

SKI Project Update 11.1.19

STEP This week, the contractor completed 5 Public Sewer house connections and installed four STEP tanks on Queen Anne Road.  Five STEP assemblies with pumps were installed on Queen Anne Road in addition to 92LF of 4” gravity sewer line installed to those individual homes. …

SKI Project Update 10.25.19

STEP The contractor has completed 3 house connections to the Public Sewer System on Queen Anne Road. Four STEP tanks were installed on Queen Anne Road.  Three STEP assemblies with pumps were installed in addition to 135LF of 4” gravity sewer line installed to…

SKI Project Update 10.11.19 and 10.18.19

STEP During the last two weeks; The contractor completed 14 house connections to the Public Sewer System on Long Point, Brick House, Queen Anne and Romancoke Roads.  Six STEP tanks were installed on Brick House, Dorchester, Romancoke and Queen Anne Roads.  Seven STEP assemblies…

SKI Project Update 10.4.19

STEP This week the contractor completed 8 house connections to the Public Sewer System on Claiborne and Long Point Road.  Three STEP tanks were installed by the contractor this week on Brick House and Queen Anne Road.  Four STEP assemblies with pumps were installed…

SKI Project Update 9.27.19

STEP This week the contractor completed 9 house connections to the Public Sewer System on Queen Anne, Long Point and Petinot Road.  One STEP tank was installed by the contractor this week on Queen Anne Road.  Seven STEP assemblies with pumps were installed along…

SKI Project Update 9.20.19

16-01 STEP This week the contractor completed all house connections on Touhey Drive; connecting 9 houses to the Public Sewer System. Two STEP tanks were installed by the contractor this week on Queen Anne Road.  Nine STEP assemblies with pumps were installed in addition…