Category: Uncategorized

Project Update 10.13.17

  STEP Contractor installed 5 tanks for the week on Utah Road, they will continue on Utah next week. We are still expecting to see the second tank crew sometime this month. County staff has acquired 759 right of entries, 592 easements and have…

SKI Project Report- September

STEP Contractor installed 19 tanks for the month. That brings the total tanks installed, as of 9-30-17, to 142. That equals about 23% of the contract amount paid to date with 21% of the contract time used. The contractor will be installing tanks on…

Project Update 09.29.17

STEP This week six tanks were set on Tennessee and Utah. The contractor will continue on Utah and South Carolina next week. County staff has acquired 585 easements to date; this brings the total to 75% of the amount required. Community Contractor installed about…

Project Update 09.22.17

STEP This week five tanks were set on Tennessee Road; contractor will continue on Tennessee next week. County staff has acquired 577 easements to date. That is about 74%  Community Contractor installed about 150lf of pipe by the open cut method on Tennessee Road….

Project Update 09.15.17

STEP Tennessee Road- The contractor set 4 tanks this week and will continue installing there next week. County staff has acquired 575 easements to date. Community The past week was spent filling the community main lines with water for pressure testing. The contractor was…

Project Update 09.08.17

STEP The contractor installed 20 tanks for the month. That brings the total number of tanks installed to 123, or 16%. The contractor has used about 19% of the contractor time. County staff continues to acquire easements and answer questions at the SKI office….

PROJECT UPDATE 08.28.17

16-01 STEP: 4 tanks were set this week on Oregon, South Carolina, and Elm Street. Contractor to continue on South Carolina and Oregon area. 16-02 Community: Contractor installed 1400 lf of pipe by the open cut and HDD method this week. Pipe was installed on Tennessee…