Category: Uncategorized

SKI Project Update 2.15.19

STEP Two rain days for the week:  One STEP Tank was installed on Queen Anne Road by the contractor this week.  The contractor also installed 5 electric meter replacements / modifications on Oregon Road.  The contractor completed one house connection to the Public Sewer…

SKI Project Update 2.8.19

STEP One STEP Tank was installed on Cecil Road by the contractor this week.  The contractor also installed 11 electric meter replacements / modifications on Oregon Road.  The contractor completed two house connections to the Public Sewer System on Cecil and North Lake Roads…

SKI Project Update 2.1.19

STEP The contractor installed 1 STEP Tank on N. Lake for the week.  This week, the contractor installed 3 electric meter replacements / modifications on Oregon Road.  The contractor completed four house connections to the Public Sewer System on Margaret Drive, Harford and Olive…

SKI Project Update 1.25.19

STEP The contractor installed 2 STEP Tanks on N. Lake and Utah Road for the week.  This week the contractor installed 5 electric meter replacements / modifications on Oregon Road.  The contractor is working on completing two house connections to the Public Sewer System…

SKI Project Update 1.18.19

STEP The contractor installed 3 STEP Tanks on Elm Street and Tennessee Road for the week.  A total of 428 STEP Tanks have been installed to date.  This week the contractor installed 5 electric meter replacements / modifications on Oregon Road.   One control panel…

SKI Project Update 1.11.19

STEP Contractor installed 8 STEP tanks on Tennessee and Romancoke Roads, Oak and Elm Street during the first two weeks of January.   The contractor installed 6 electric meter replacements / modifications on Maryland and New Jersey Roads, Oak and Elm Street for the first…

SKI Project Update 1.4.19

STEP Not much progress this week; Merry Christmas and Happy New Year!