Category: Uncategorized

SKI Project update 7.31.22

Previous (2021)  work completed 33 connections. 21-01 STEP For the month of July 2022  SKI Sewer Project Phase 2 Tower Gardens the contractor installed 9 STEP tanks and completed 9 house connections on North Lake Drive. Along with other utility requirements and yard restorations… Continue Reading “SKI Project update 7.31.22”

June 30th, 2022- Southern Kent Island (SKI) Sanitary Project Phase 2

Previous work completed 33 connections on North Lake Drive. 21-01 STEP On May 25th, 2022 – SKI Sewer Project Phase 2 Tower Gardens resumed construction by Cole Ventures, Inc.  to the remaining 168 homes.  Public sewer construction has re-started installing STEP tanks, continuing with… Continue Reading “June 30th, 2022- Southern Kent Island (SKI) Sanitary Project Phase 2”

16-01 STEP

Queen Anne’s County Sanitary District SKI STEP Sewer Service User Information How does my STEP System work? STEP means Septic Tank Effluent Pump.  Your STEP system includes a holding tank for sewage, a screen chamber and a small high-pressure pump within the tank.   The… Continue Reading “16-01 STEP”

SKI Project Update 10.31.21

16-01 STEP Since July the contractor continues to complete yard restorations and submit finalized as- builts to the SKI Community Office. 20-01 STEP June – August the contractor installed 33 STEP Tanks and connected 32 homes to the Public Sewer System.  Tower Gardens sewer… Continue Reading “SKI Project Update 10.31.21”

SKi Project Update 7.31.21

SKI 16-01 STEP For the months of May – July 31st  2021, the contractor installed 39 STEP tanks and completed 82 house connections to the Southern Kent Island Public Sewer System.  There are a few houses that have not been connected to the Public… Continue Reading “SKi Project Update 7.31.21”

SKI Project Update 4.30.21

For the months of March and April 2021, the contractor completed 63 house connections to the Southern Kent Island public sewer system along with septic tank abandonments. Nineteen tanks were installed.  The contractor continues with daily yard stabilization and restoration.  Late spring into early… Continue Reading “SKI Project Update 4.30.21”

SKI Project Update 2.28.21

SKI 16-01 STEP For the months of January and February 2021, the contractor completed 46 house connections to the Southern Kent Island public sewer system; those locations include: Elm Street, Penny Lane, Caroline, Talbot, Tennessee, Wicomico and Worcester Roads.   The contractor worked on finalizing… Continue Reading “SKI Project Update 2.28.21”

SKI Project Update 12.31.2020

16-01 STEP For the months of November and December 2020, the contractor completed 61 house connections to the Southern Kent Island public sewer system; those locations included Bay Drive, Maryland, North Lake, South Carolina, Utah, Romancoke, Claiborne, Saint Mary’s, Worcester, Talbot, Somerset and Wicomico… Continue Reading “SKI Project Update 12.31.2020”

Southern Kent Island Sanitary Project Update No. 3

SKI Project Update 10.31.20

For the month of October 2020, the contractor completed 33 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Bay Drive, Talbot, Worcester, Caroline, Somerset and Utah Roads.  Eleven STEP tanks were installed on Bay Drive, Caroline, Somerset… Continue Reading “SKI Project Update 10.31.20”