Category: Uncategorized

Project Update 08.18.17

STEP Contractor installed 6 tanks this week on Oregon Road. County staff received 4 more easements. This brings the total easements collected to 565. This is 73% of the total number of easements. Next week, the contractor is planning on installing tanks on Oregon,…

Project Update- 08.11.17

STEP Two tanks were installed this week on Tennessee Road by the contractor. Contractor will continue with tank installations on Oregon Road next week. County staff obtained 8 more easements bringing the total to 561 or 72% of all the easements. Community The contractor…

Project Update- July 2017

STEP The contractor installed 18 tanks during the month of July. That brings the total number of tanks installed to 103, which is about 13% of the total tanks. The contractor has used about 17% of the contract time. The contractor is expecting to…

Project Update 07.28.17

STEP Contractor installed 4 tanks for the week. That puts the total tanks installed to 102. Contractor will continue to install tanks on Tennessee next week. County staff also acquired 3 more easement to bring the total to 540 which is about 70% completed. …

SKI Office will be closing today, July 25, at 4:00 PM.

Project Update 07.21.17

STEP Contractor installed 6 tanks for the week on South Carolina Road; tank installation will continue next week on Tennessee Road. We should break 100 tanks being installed sometime next week.  County staff held pre-construction meetings and acquired more easements. The current easement total…

Project Update 07.14.17

STEP Contractor installed 5 tanks this week on Oregon Road. County staff acquired another 14 easements to bring the total to 533 to date which is about 69% of all easements. Contractor will continue to install tanks on South Carolina next week. Community Contractor…