Previous (2021) work completed 33 connections 21-01 STEP (200 Existing Homes) Progress for the months of March and April 2023, SKI Sewer Project Phase 2 – Tower Gardens. The contractor completed installing 23 STEP tanks and connecting 24 houses to Public Sewer. Those installs… Continue Reading “SKI STEP Phase 2 & COMMUNITY MAIN SEWER Phase 3 PROJECT UPDATE 4.30.23”
Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of January and February 2023, SKI Sewer Project Phase 2- Tower Gardens. The contractor completed installing 25 STEP tanks and 25 house connections to Public Sewer. Those installs and connections completed Drovers… Continue Reading “SKI STEP Sewer Project Update 2.28.23”
16-01 STEP – RECAP Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of November and December 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive and on December 1st began… Continue Reading “SKI Sewer Project Update 12.31.22”
Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive. 20 STEP tanks were installed along with the completion… Continue Reading “SKI Sewer Project Update 10.31.22”
22-02 Phase 3 Community Mains For the months of July and August 2022 the contractor has drilled and installed pipe for the community mains in the Kentmorr sub-division. The contractor has moved to Queens Colony High Road to drill and install 6” pipe for… Continue Reading “SKI Sewer Project Update 8.31.22”
21-01 Phase 2 STEP Previous (2021) work completed 33 connections. For the month of August 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 15 STEP tanks and completed 13 house connections on North Lake and Beachside Drive, in addition to other… Continue Reading “SKI Sewer Project Update 8.31.2022”
Previous (2021) work completed 33 connections. 21-01 STEP For the month of July 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 9 STEP tanks and completed 9 house connections on North Lake Drive. Along with other utility requirements and yard restorations… Continue Reading “SKI Project update 7.31.22”
Previous work completed 33 connections on North Lake Drive. 21-01 STEP On May 25th, 2022 – SKI Sewer Project Phase 2 Tower Gardens resumed construction by Cole Ventures, Inc. to the remaining 168 homes. Public sewer construction has re-started installing STEP tanks, continuing with… Continue Reading “June 30th, 2022- Southern Kent Island (SKI) Sanitary Project Phase 2”
Queen Anne’s County Sanitary District SKI STEP Sewer Service User Information How does my STEP System work? STEP means Septic Tank Effluent Pump. Your STEP system includes a holding tank for sewage, a screen chamber and a small high-pressure pump within the tank. The… Continue Reading “16-01 STEP”
16-01 STEP Since July the contractor continues to complete yard restorations and submit finalized as- builts to the SKI Community Office. 20-01 STEP June – August the contractor installed 33 STEP Tanks and connected 32 homes to the Public Sewer System. Tower Gardens sewer… Continue Reading “SKI Project Update 10.31.21”