SKI Project Update 7.6.18

16-01 The contractor installed 5 step tanks for the week on Pennick Drive, Olive Branch and Long Point Roads.  They also drilled 735lf of 1” pressure sewer line on Utah Road.   The contractor will continue drill shots on Utah Road next week.  County Staff…

SKI Project Update 6.29.18

16-01 Step Contractor installed 7 step tanks for the week on Wicomico, Carroll and Pennick Roads. They also drilled 695lf of 1″ pressure sewer line from the property line to the step tanks.  Long Point and Romancoke Roads Electric Meter Installs will begin next…

SKI Project Update 6.22.18

Step Contractor installed 7 step tanks for the week on Baltimore, Romancoke and Wicomico Roads. They also drilled 493lf of 1″ pressure sewer line from the property line to the step tanks on Tennessee Road. The Electric meter installs will begin again next week…

SKI Project Update 6.15.18

  Step The contractor installed 5 step tanks for the week on Wicomico, Dorchester and Baltimore Roads.  They also drilled 629lf of 1″ pressure sewer line from the property line to the step tanks.  The contractor installed 6 electric meter replace / modification on…

SKI Project Update May 2018

May rain fall recorded at the SKI office was over 10 inches.   STEP Contractor had a productive month in spite of the rain. The contractor installed 17 STEP tanks on Wicomico, Washington, and Kent Roads. They installed 35 Bio-tubes in previously installed tanks…

SKI Project Update 6.1.18

Step Contractor installed 5 tanks for the week on Wicomico, Kent and Washington Roads.  They also ran 483lf of 1″ service lines from the street to previously installed tanks with bio-tube less pump.  The contractor installed 5 electric meter replace and 1 electric meter…

SKI PROJECT UPDATE 5.25.18

Step Contractor installed 4 tanks for the week on Wicomico, Kent and Dorchester Roads.  They also ran 238lf of 1″ service lines from the street to previously installed tanks.  The contractor also changed out 11 electrical meter boxes on Long Point and Allegany.   Electric…

SKI Project update 5.18.18

Step – Community – Transmission RAIN Over 6.5 inches of rain was recorded at the SKI office from Monday morning thru Friday noon. No work by the contractors this week.   Early next week not looking much better before mid-week.  

Project Update 5.11.18

Step Contractor installed 5 step tanks for the week on Wicomico.  They also ran about 565lf 1″ service lines from the property line to the step tank.  The contractor also changed out 10 electrical meter boxes on Allegany.  Electrical Meter Replace/ Electric Meter Modification…

SKI Project Update 5.04.18

STEP Contractor installed 17 tanks for the month on Wicomico and Talbot Roads. They also installed about 2400 lf of 1″ service line from the street to previously installed tanks on New Jersey and Oak Street. The contractor also changed out or modified 25…

Project Update 04.27.18

STEP Contractor installed 5 tanks on Talbot and Wicomico Roads for the week. The contractor also installed about 590lf of 1” service line from previously installed tanks to the street on Oregon Road. Contractor will continue installing tanks on Wicomico next week. Electrical connections…

SKI Project Update 4.20.18

16-01 Contractor installed 5 tanks for the week on Wicomico Road.  They also ran about 500lf of 1″ service lines from the street to previously installed tanks.  The contractor also changed out 6 electrical meter boxes on New Jersey.  Electric meter modifications / change…