SKI Project Update 4.3.20

STEP

The contractor completed seven house connections to the public sewer system located on Romancoke, Long Point, N. Lake and Dorchester Roads and two STEP tanks were installed on Cecil and Romancoke Roads.  Six electric meter replacements / modifications were installed by the contractor this week on Talbot, N. Lake and Dorchester Roads.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue sewer utility operations on Dorchester and South Carolina Roads.   Locations are subject to change.   SKI sewer work street signs will be updated and posted.   County staff has performed 669 pre- construction meetings and acquired 761 easements to date.

  • County staff has performed 36 post-construction site visits to date.
  • The contractor has installed 589 STEP tanks to date.
  • The contractor has connected 291 houses to the public sewer system to date.

443c0d38-cdee-41e9-a05d-679e272df622

62c76929-a51b-46fa-b9d8-46dd6a0d745ab1a1c322-e2d5-4bfc-b61e-0ff687c0f7d5

%d bloggers like this: