Category: Uncategorized

SKI Project Update 2.28.20

STEP This week the contractor completed five house connections to the public sewer system on Oregon and Long Point Road and two STEP tanks were installed on Dorchester and Long Point Road.  Five electric meter replacements / modifications were installed by the contractor this… Continue Reading “SKI Project Update 2.28.20”

SKI Project Update 2.21.2020

STEP This week the contractor completed seven house connections to the public sewer system on Dorchester, Oregon and Long Point Road and three STEP tanks were installed on Dorchester and Long Point Road. Eleven electric meter replacements / modifications were installed by the contractor… Continue Reading “SKI Project Update 2.21.2020”

SKI Project Update 2.7.2020

STEP The rain this week limited sewer installation progress;  the contractor completed three house connections to the public sewer system and installed one STEP tank on Dorchester Road.   Five electric meter replacements / modifications were installed by the contractor this week on Somerset Road.… Continue Reading “SKI Project Update 2.7.2020”

SKI Project Update 1.31.2020

STEP This week the contractor completed five house connections to the public sewer system and installed four STEP tanks on Pennick Drive, Point, Dorchester and Oregon Roads. Five electric meter replacements / modifications were installed by the contractor this week on Somerset Road along… Continue Reading “SKI Project Update 1.31.2020”

SKI Project Update 1.24.2020

STEP This week the contractor completed five house connections to the public sewer system and installed four STEP tanks on Queen Anne and Point Road.  Eleven electric meter replacements / modifications were installed by the contractor this week on Talbot, Somerset and Long Point… Continue Reading “SKI Project Update 1.24.2020”

SKI Project Update 1.17.2020

STEP This week the contractor completed four house connections to the public sewer system and installed four STEP tanks on Queen Anne Road.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue utility operations; drilling 1” service lines,… Continue Reading “SKI Project Update 1.17.2020”

SKI project update 01.10.2020

STEP This week the contractor completed five house connections to the public sewer system and installed four STEP tanks on Queen Anne Road.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue with utility operations; drilling 1” service… Continue Reading “SKI project update 01.10.2020”

SKI Project Update 01.03.2020

STEP For the weeks ending 12.27.19 and 01.03.2020 the contractor completed four house connections to the public sewer system and installed five STEP tanks on Queen Anne Road.  The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue utility… Continue Reading “SKI Project Update 01.03.2020”

SKI Project Update 12.20.19

STEP The contractor had a slow week due to rain and unfavorable weather conditions.   This week, two house connections to the public sewer system and three STEP tank installs were completed on Queen Anne Road. The contractor continues with daily yard stabilization and restorations. … Continue Reading “SKI Project Update 12.20.19”

SKI Project Update 12.6.19

STEP For the weeks ending 11/29 and 12/6/19 the contractor completed 6 house connections to the Public Sewer System and installed Five STEP tanks on Queen Anne and North Lake Road.   The contractor installed 244 LF of 4” gravity sewer line to those individual… Continue Reading “SKI Project Update 12.6.19”