SKI Project Update 1.24.2020

STEP

This week the contractor completed five house connections to the public sewer system and installed four STEP tanks on Queen Anne and Point Road.  Eleven electric meter replacements / modifications were installed by the contractor this week on Talbot, Somerset and Long Point Roads.  The contractor continues with daily yard stabilization and restorations.   Next week, the contractor expects to complete sewer utility operations on Point Road.  Locations are subject to change.   SKI sewer work street signs will be updated and posted.   County staff has performed 650 pre- construction meetings and acquired 757 easements to date.

  • County staff has performed 36 post-construction meetings to date.
  • The contractor has installed 565 STEP tanks to date.
  • The contractor has connected 232 houses to the public sewer system to date.