STEP The contractor had a slow week due to rain and unfavorable weather conditions. This week, two house connections to the public sewer system and three STEP tank installs were completed on Queen Anne Road. The contractor continues with daily yard stabilization and restorations. … Continue Reading “SKI Project Update 12.20.19”
STEP For the weeks ending 11/29 and 12/6/19 the contractor completed 6 house connections to the Public Sewer System and installed Five STEP tanks on Queen Anne and North Lake Road. The contractor installed 244 LF of 4” gravity sewer line to those individual… Continue Reading “SKI Project Update 12.6.19”