Day: December 20, 2019

SKI Project Update 12.20.19

STEP The contractor had a slow week due to rain and unfavorable weather conditions.   This week, two house connections to the public sewer system and three STEP tank installs were completed on Queen Anne Road. The contractor continues with daily yard stabilization and restorations. … Continue Reading “SKI Project Update 12.20.19”