STEP This week the contractor completed five house connections to the public sewer system on Oregon and Long Point Road and two STEP tanks were installed on Dorchester and Long Point Road. Five electric meter replacements / modifications were installed by the contractor this… Continue Reading “SKI Project Update 2.28.20”
STEP This week the contractor completed seven house connections to the public sewer system on Dorchester, Oregon and Long Point Road and three STEP tanks were installed on Dorchester and Long Point Road. Eleven electric meter replacements / modifications were installed by the contractor… Continue Reading “SKI Project Update 2.21.2020”
STEP The rain this week limited sewer installation progress; the contractor completed three house connections to the public sewer system and installed one STEP tank on Dorchester Road. Five electric meter replacements / modifications were installed by the contractor this week on Somerset Road.… Continue Reading “SKI Project Update 2.7.2020”