SKI Project Update 2.28.20

STEP This week the contractor completed five house connections to the public sewer system on Oregon and Long Point Road and two STEP tanks were installed on Dorchester and Long Point Road.  Five electric meter replacements / modifications were installed by the contractor this… Continue Reading “SKI Project Update 2.28.20”