STEP
This week the contractor completed five house connections to the public sewer system on Oregon and Long Point Road and two STEP tanks were installed on Dorchester and Long Point Road. Five electric meter replacements / modifications were installed by the contractor this week on Somerset, Talbot and Kent Road. The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Dorchester, Oregon and Long Point Road. Locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 656 pre- construction meetings and acquired 759 easements to date.