SKI Project Update 2.21.2020

STEP

This week the contractor completed seven house connections to the public sewer system on Dorchester, Oregon and Long Point Road and three STEP tanks were installed on Dorchester and Long Point Road. Eleven electric meter replacements / modifications were installed by the contractor this week on Somerset and Oregon Road.   The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue sewer utility operations on Dorchester, Oregon and Long Point Road.   Locations are subject to change.   SKI sewer work street signs will be updated and posted.   County staff has performed 654 pre- construction meetings and acquired 759 easements to date.

  • County staff has performed 36 post-construction site visits to date.
  • The contractor has installed 576 STEP tanks to date.
  • The contractor has connected 250 houses to the public sewer system to date.