SKI Project Update 2.7.2020

STEP

The rain this week limited sewer installation progress;  the contractor completed three house connections to the public sewer system and installed one STEP tank on Dorchester Road.   Five electric meter replacements / modifications were installed by the contractor this week on Somerset Road. The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue sewer utility operations on Dorchester and Oregon Roads.   Locations are subject to change.   SKI sewer work street signs will be updated and posted.   County staff has performed 651 pre- construction meetings and acquired 757 easements to date.

  • County staff has performed 36 post-construction meetings to date.
  • The contractor has installed 570 STEP tanks to date.
  • The contractor has connected 240 houses to the public sewer system to date.