STEP
This week the contractor completed five house connections to the public sewer system and installed four STEP tanks on Pennick Drive, Point, Dorchester and Oregon Roads. Five electric meter replacements / modifications were installed by the contractor this week on Somerset Road along with two meter re-locations on Oregon Road and Pennick Drive. The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Dorchester and Oregon Roads. Locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 651 pre- construction meetings and acquired 757 easements to date.