Day: January 3, 2020

SKI Project Update 01.03.2020

STEP For the weeks ending 12.27.19 and 01.03.2020 the contractor completed four house connections to the public sewer system and installed five STEP tanks on Queen Anne Road.  The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue utility… Continue Reading “SKI Project Update 01.03.2020”