For the weeks ending 12.27.19 and 01.03.2020 the contractor completed four house connections to the public sewer system and installed five STEP tanks on Queen Anne Road. The contractor continues with daily yard stabilization and restorations.
Next week, the contractor will continue utility operations; drilling 1” service lines, installing STEP tanks and house connections on Queen Anne Road. Locations are subject to change. Signs will be updated and posted.
County staff has performed 648 pre- construction meetings and acquired 757 easements to date.