SKI Project Update 3.6.20

16-01 STEP

This week the contractor completed seven house connections to the public sewer system on Bay Drive, Oregon, Long Point and Utah Road and three STEP tanks were installed on Cecil, Dorchester and Long Point Road. Ten electric meter replacements / modifications were installed by the contractor this week on Talbot Caroline and Romancoke Road.  The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Dorchester, Cecil, Oregon and Long Point Road. Locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 661 pre- construction meetings and acquired 761 easements to date.

  • County staff has performed 36 post-construction site visits to date.
  • The contractor has installed 581 STEP tanks to date.
  • The contractor has connected 262 houses to the public sewer system to date.

 

749c4820-77dc-4531-a2a1-cb38a1533eb09c56f9fa-2011-4a67-bcf5-dff0e1ee0207c43a0290-fa1d-44a0-94ff-d0bc9c1ff108

%d bloggers like this: