SKI Project Update 3.20.20

STEP

This week the contractor completed eight house connections to the public sewer system located on Penny Lane, Oregon, Dorchester and Romancoke Road and four STEP tanks were installed on Romancoke and Oregon Road. Six electric meter replacements / modifications were installed by the contractor this week on Talbot and Dorchester Road. The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Dorchester, Oregon and Long Point Road. Locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 669 pre- construction meetings and acquired 761 easements to date.

  • County staff has performed 36 post-construction site visits to date.
  • The contractor has installed 586 STEP tanks to date.
  • The contractor has connected 278 houses to the public sewer system to date.