SKI Project Update 4.30.21

For the months of March and April 2021, the contractor completed 63 house connections to the Southern Kent Island public sewer system along with septic tank abandonments. Nineteen tanks were installed.  The contractor continues with daily yard stabilization and restoration.  Late spring into early… Continue Reading “SKI Project Update 4.30.21”

SKI Project Update 2.28.21

SKI 16-01 STEP For the months of January and February 2021, the contractor completed 46 house connections to the Southern Kent Island public sewer system; those locations include: Elm Street, Penny Lane, Caroline, Talbot, Tennessee, Wicomico and Worcester Roads.   The contractor worked on finalizing… Continue Reading “SKI Project Update 2.28.21”

SKI Project Update 12.31.2020

16-01 STEP For the months of November and December 2020, the contractor completed 61 house connections to the Southern Kent Island public sewer system; those locations included Bay Drive, Maryland, North Lake, South Carolina, Utah, Romancoke, Claiborne, Saint Mary’s, Worcester, Talbot, Somerset and Wicomico… Continue Reading “SKI Project Update 12.31.2020”

Southern Kent Island Sanitary Project Update No. 3

SKI Project Update 10.31.20

For the month of October 2020, the contractor completed 33 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Bay Drive, Talbot, Worcester, Caroline, Somerset and Utah Roads.  Eleven STEP tanks were installed on Bay Drive, Caroline, Somerset… Continue Reading “SKI Project Update 10.31.20”

SKI Project Update 9.30.20

16-01 STEP For the month of September 2020, the contractor completed 26 house connections to the Southern Kent Island public sewer system; those locations were Bay Drive, Beach, Somerset, South Carolina Talbot, Tennessee and Utah Roads.  Seventeen STEP tanks were installed on Beach, Somerset,… Continue Reading “SKI Project Update 9.30.20”

SKI Project Update 8.31.20

16-01 STEP For the month of August 2020, the contractor completed 23 house connections to the Southern Kent Island public sewer system; those locations were Somerset, Talbot, Tennessee and Wicomico Roads.  Twelve STEP tanks were installed on Somerset, Talbot and Tennessee Roads.  Ten electric… Continue Reading “SKI Project Update 8.31.20”

ski project update 7.31.20

16-01 STEP For the month of July, 2020 the contractor completed 34 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Somerset, Talbot and Tennessee Roads.  Nineteen STEP tanks were installed on Elm Street, Somerset, Talbot, Tennessee Roads. … Continue Reading “ski project update 7.31.20”

SKi project notice

Southern Kent Island Sewer Residents Prior to installing a fence on your property, the Sanitary District requires the Sewer Control Panel to have an unobstructed line of sight to the tank. The Easement Documentation requires 5 feet distance from either side of the tank… Continue Reading “SKi project notice”

SKI PROJECT UPDATE 6.30.20

16-01 STEP For the months of May and June, 2020 the contractor completed 79 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Petinot and Margaret Drive, Baltimore, Dorchester, Kent, Maryland, New Jersey, North Lake, Oregon, Romancoke, Somerset,… Continue Reading “SKI PROJECT UPDATE 6.30.20”