STEP
For the Month of May the contractor completed 28 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Margaret Drive, South Carolina, Oregon, New Jersey, Dorchester, Kent, Maryland, Washington and Baltimore Roads. Twelve STEP tanks were installed on Margaret Drive, Talbot, Baltimore and Washington Roads. The contractor installed 15 electric meter replacements / modifications for the month. The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Margaret and Petinot Drive, locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 680 pre- construction meetings and acquired 761 easements to date.