STEP
For the weeks ending 4/24 and 5/1/2020 the contractor completed 17 house connections to the Southern Kent Island public sewer system; those locations were Oak Street, Romancoke, South Carolina, Oregon, New Jersey, Talbot and Baltimore Roads. Five STEP tanks were installed on Talbot, Romancoke and Baltimore Roads. The contractor installed 9 electric meter replacements / modifications for both weeks on Utah Roads. The contractor continues with daily yard stabilization and restorations. Next week, the contractor will continue sewer utility operations on Oak Street, Oregon, Dorchester, New Jersey, Baltimore and Talbot Roads. Locations are subject to change. SKI sewer work street signs will be updated and posted. County staff has performed 677 pre- construction meetings and acquired 761 easements to date.