For the month of July 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 9 STEP tanks and completed 9 house connections on North Lake Drive.
Along with other utility requirements and yard restorations the contractor only has 5 houses remaining on North Lake Dr before heading to Beachside Dr.
County Staff has performed a total of 133 pre-construction meetings and acquired 196 easements to date.
The contractor has installed 22 STEP tanks to date.
The contractor has connected 22 Houses to the public sewer system to date.
control panelslicing the turf to begin dig for install & equipment mats1 house 2 connections- 4″ Gravity to STEP tank with cleanout STEP tank risers and Stone backfill for STEP Tank Electrical Conduit