For the month of August 2022 SKI Sewer Project Phase 2 Tower Gardens the contractor installed 15 STEP tanks and completed 13 house connections on North Lake and Beachside Drive, in addition to other utility requirements and yard restorations. Pre-construction meetings and electric meter work will begin on Drovers Way.
County Staff has performed a total of 113 pre-construction meetings and acquired 197 easements to date.
The contractor has installed 37 STEP tanks to date.
The contractor has connected 35 Houses to the public sewer system to date.
Total homes connected to the public sewer system to date 68.