SKI Sewer Project Update 8.31.2022

21-01 Phase 2 STEP

Previous (2021)  work completed 33 connections.

For the month of August 2022  SKI Sewer Project Phase 2 Tower Gardens the contractor installed 15 STEP tanks and completed 13 house connections on North Lake and Beachside Drive, in addition to other utility requirements and yard restorations.   Pre-construction meetings and electric meter work will begin on Drovers Way.

  • County Staff has performed a total of 113 pre-construction meetings and acquired 197 easements to date.
  • The contractor has installed 37 STEP tanks to date.
  • The contractor has connected 35 Houses to the public sewer system to date.
  • Total homes connected to the public sewer system to date 68.