Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive. 20 STEP tanks were installed along with the completion… Continue Reading “SKI Sewer Project Update 10.31.22”