SKI Sewer Project Update 10.31.22

Previous (2021) work completed 33 connections

21-01 STEP

Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens.  The contractor continues public sewer utility operations on Beachside Drive.   20 STEP tanks were installed along with the completion of 22 house connections following up with yard restoration at each property.   Pre-construction meetings are wrapping up on Drovers Way and Calvert Drive.   Next on the pre-con schedule will be Oxbow Dr. and South Lake Dr.    Electric meter work will continue on Drovers Way moving forward to Calvert Dr. 

  • County staff has performed a total of 132 Pre-construction meetings and acquired 196 Easements to date.
  • The contractor has installed 57 STEP tanks to date.
  • The contractor has connected 57 houses to the public sewer system to date. 
  • Total phase 2 homes connected to public sewer system is 90 to date .

22-02 Community Mains

Progress from July to October 2022, SKI Sewer Project Phase 3 CM Kentmorr & Queen Anne Colony  –  17,290 LF of HDPE pressure sewer main pipe has been directional drilled and tied in at Kentmorr and Queen Anne Colony. 

Sewer pipe work on the community main will continue in both developments.

  • County staff has acquired 153 easements to date.