Previous (2021) work completed 33 connections
21-01 STEP
Progress for the months of September and October 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive. 20 STEP tanks were installed along with the completion of 22 house connections following up with yard restoration at each property. Pre-construction meetings are wrapping up on Drovers Way and Calvert Drive. Next on the pre-con schedule will be Oxbow Dr. and South Lake Dr. Electric meter work will continue on Drovers Way moving forward to Calvert Dr.
22-02 Community Mains
Progress from July to October 2022, SKI Sewer Project Phase 3 CM Kentmorr & Queen Anne Colony – 17,290 LF of HDPE pressure sewer main pipe has been directional drilled and tied in at Kentmorr and Queen Anne Colony.
Sewer pipe work on the community main will continue in both developments.