The contractor installed 773 STEP tanks. 1 remaining.
The contractor connected 769 houses to the public sewer system, with an exception of 5 remaining that are either pending demolition and/or construction.
Previous (2021) work completed 33 connections
21-01 STEP
Progress for the months of November and December 2022, SKI sewer Project Phase 2 – Tower Gardens. The contractor continues public sewer utility operations on Beachside Drive and on December 1st began installs and house connections Drovers Way . 19 STEP tanks were installed along with the completion of 18 house connections while following up with yard restoration at each property. Pre-construction meetings are currently being scheduled for Oxbow and South Lake Drive . Electric meter work will continue on Calvert moving forward to Oxbow Drive .
County staff has performed a total of 149 Pre-construction meetings and acquired 196 Easements to date.
The contractor has installed 76 STEP tanks to date.
The contractor has connected 75 houses to the public sewer system to date.
Total phase 2 homes connected to public sewer system is 108 to date .
Progress from November to December 2022, SKI Sewer Project Phase 3 CM Kentmorr & Queen Anne Colony – 29,131. LF of HDPE pressure sewer main pipe has been directional drilled and tied in at Kentmorr and Queen Anne Colony.
Sewer pipe work on the community main will continue in both developments.