SKI STEP Sewer Project Update 2.28.23

Previous (2021) work completed 33 connections 21-01 STEP Progress for the months of January and February 2023,  SKI Sewer Project Phase 2- Tower Gardens. The contractor completed installing 25 STEP tanks and 25 house connections to Public Sewer.  Those installs and connections completed  Drovers… Continue Reading “SKI STEP Sewer Project Update 2.28.23”