Previous (2021) work completed 33 connections
21-01 STEP (200 Existing Homes)
Progress for the months of March and April 2023, SKI Sewer Project Phase 2 – Tower Gardens.
The contractor completed installing 23 STEP tanks and connecting 24 houses to Public Sewer.
Those installs and connections completed Oxbow Drive, picked up a few on Tower and almost
half of South Lake Dr & Ct. During the upcoming months sewer utility work will continue on South Lake Drive
moving forward to King George Ct, Tower Drive and Kent Point Rd.
Yard Restoration (backfilling & seeding) will be ongoing and continue throughout the end of phase 2.
Only 23 remaining properties in phase 2 require electric meter work.
22-02 Community Main (340 Existing Homes)
Progress for the months of March and April 2023, SKI Sewer Project Phase 3 Community Main Kentmorr and Queen Anne Colony
169 LF of 3” and 4” HDPE Pressure sewer main was directional drilled and tied in.
Out of 126 properties in Kentmorr 98 curb stops have been installed.