Southern Kent Island Sewer Project Update May 24, 2024

Phase 3 Kentmorr & Queen Anne Colony: STEP tank placement began in January 2024, in the Kentmorr Community. Since that time 42 STEP tanks have been installed and connected to the public sewer. Cole Ventures is projected to have the community of Kentmorr completed… Continue Reading “Southern Kent Island Sewer Project Update May 24, 2024”