Month: March 2021

SKI Project Update 2.28.21

SKI 16-01 STEP For the months of January and February 2021, the contractor completed 46 house connections to the Southern Kent Island public sewer system; those locations include: Elm Street, Penny Lane, Caroline, Talbot, Tennessee, Wicomico and Worcester Roads.   The contractor worked on finalizing… Continue Reading “SKI Project Update 2.28.21”