Day: January 30, 2017

Project Update 01.27.17

STEP 2 tanks were installed this week. Rain slowed down progress for this week. MDE project signs have been place. Tanks continue to be installed. Community Collection Lines Still waiting on pipe delivery. MDE sign placed. Transmission main will be crossing Maryland and New… Continue Reading “Project Update 01.27.17”