Month: February 2017

Project Update 02.27.17

STEP The County acquired 9 additional easements on Margaret Drive.  The contractor was preparing a water truck for testing the tanks and mobilizing to Margaret to start installing tanks on Monday 27th. Community Collection Mains The Contractor set up for Horizontal Direction Drill (HDD)…

Project Update 02.23.17

Community Collection Line  Horizontal Directional Drilling (HDD) for the placement of a 3-inch community main will begin on Touhey Drive starting on Thursday, February 23.

Project Update 02.17.17

STEP Contractor has one more tank to install on Touhey. This tank will be installed on Monday, 02/20/17. The contractor will then move to Margaret Drive to start installing tanks on 02/27/17. The contractor will be using next week to complete restoration on Touhey…

Project Update 02.03.17

STEP 3 pre-construction meetings were held this week and 8 easements were acquired. No tanks were installed this week, will continue to install tanks next week. Contractor has 13 more tanks to install before the end of February. Community Collection Mains Marking out tee…