Project Update 02.03.17

STEP

3 pre-construction meetings were held this week and 8 easements were acquired. No tanks were installed this week, will continue to install tanks next week. Contractor has 13 more tanks to install before the end of February.

Community Collection Mains

Marking out tee locations for community mains.

Force Main

Contractor installed approx. 1800 feet of 12″ HDPE and 14″ PVC this week. Will continue to install pipe next week on North end of project crossing Gravel Drive, Sassafras Lane, Colburn View, San Cedra and as far as Bay View. The South end will be working between Kent Road and Touhey Drive.

 

 

 