The SKI Sewer Project will be staging sewer force main pipe from Matapeake School area to north of Blunt Marsh Road near the Cloisters project. Pipe will be moved on Thursday, May 18 at 1:00 pm; there will be an active lane closure. A second… Continue Reading “Project Update-05/15/17”
STEP 4 Step Tanks were installed this week on Maryland and New Jersey Roads. Contractor will continue on these roads next week. County staff acquired 7 more easements and held 8 pre-construction meetings. We have about 63% of the total number of easements. Community… Continue Reading “Project Update- 06.16.17”