Project Update-05/15/17

The SKI Sewer Project will be staging sewer force main pipe from Matapeake School area┬áto north of Blunt Marsh Road near the Cloisters project. Pipe will be moved on Thursday, May 18 at 1:00 pm; ┬áthere will be an active lane closure. A second… Continue Reading “Project Update-05/15/17”

Project Update- 06.16.17

STEP 4 Step Tanks were installed this week on Maryland and New Jersey Roads. Contractor will continue on these roads next week. County staff acquired 7 more easements and held 8 pre-construction meetings. We have about 63% of the total number of easements. Community… Continue Reading “Project Update- 06.16.17”