STEP Office staff acquired 3 more easements this week for a total of 568 which equal 73 % of the required easements for the project. Contractor installed four tanks on Oregon, Elm and South Carolina Roads. The contractor and Project representative attended 4 more… Continue Reading “Project Update 08.25.17”