STEP     

Office staff acquired 3 more easements this week for a total of 568 which equal 73 % of the required easements for the project.   Contractor installed four tanks on Oregon, Elm and South Carolina Roads.  The contractor and Project representative attended 4 more preconstruction meetings. Door Notices for homeowner pre construction meeting scheduling were placed on Virginia Road West and Lake Roads.

Community

2000 linear feet of pipe was installed on Utah Road. Contractor began installation of Spur lines on Romancoke Road.

Transmission

Contractor installed the remaining 100 linear feet of pipe to connect the airport line to the line under Pier One Road. Restoration of the area has been underway.