SKI Project Update 10.31.20

For the month of October 2020, the contractor completed 33 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Bay Drive, Talbot, Worcester, Caroline, Somerset and Utah Roads.  Eleven STEP tanks were installed on Bay Drive, Caroline, Somerset… Continue Reading “SKI Project Update 10.31.20”