Queen Anne’s County Sanitary District will be performing routine sewer tank maintenance on your STEP System.
Phase 1 – Kent Island Estates and Romancoke on the Bay.
A Homeowner’s Guide to Septic Tank Effluent (STEP) Systems
system. County sanitary utility workers will be inspecting your tank at least every 5 years
and will be pumping out the solids as needed.
Previous (2021) work completed 33 connections
21-01 STEP
SKI Sewer Project Phase 2, Tower Gardens- Progress for the months of May and June 2023: The contractor installed 21 STEP tanks and connected 21 homes to public sewer. Those installs and connections completed South Lake Dr and Court, with startup beginning on Tower Dr. and King George Ct. Only 4 remaining properties require Electric Meter work. Yard Restoration (backfilling settled areas and seeding) will be ongoing and continue throughout the end of phase 2, be mindful that re-seeding will take place in September.
Moving forward, the contractor plans to finish up sewer services on Tower Dr, King George Ct. and Kent Point Rd. next month before returning to a few other properties in the Tower Gardens community to complete phase 2 public sewer.
22-02 Community Mains (341 Existing Homes)
SKI Sewer Project Phase 3, Kentmorr and Queen Anne Colony Progress for the months of May and June 2023:
The contractor has installed 141 sewer curb stop valves and tied in 3,499. LF of SDR7 pressure service tubing.
Kentmorr subdivision community mains will soon be completed when the air release valves are installed. Public sewer community main operations have moved forward to Queen Anne Colony subdivision.






