STEP Contract
Contractor and QAC Staff held 5 Homeowner interviews. Contractor installed 2 STEP tanks. Four tanks scheduled to be installed on Touhey Drive this week. Interviews will be continuing. …
Community Collection Lines:
Continuing to mark curb stop locations with wooden stakes in the Community. The contractor staked out collection lines on Touhey and Margaret. We are expecting pipe delivery and community line installs mid-February.
Force Main
Contractor installed 2,300 feet of 14-inch pvc pipe at Kentmorr and behind the Sanitary District treatment plant from RT 50. Contractor also fused about 2,000 feet of 12-inch HDPE pipe near the Golf course driving range. He will be installing this pipe next week along with continuing the 14-inch install near Cranny Creek Lane and Porter Farm Lane along MD 8.