Project Update 07.07.17

STEP 2 tanks were installed this week on Oregon Road, work should continue on Oregon next week. Office staff have acquired 522 easements (68%) to date. Community Contractor installed about 700 lf of pipe on Maryland and South Carolina Roads by the HDD and…