Project Update 07.07.17

STEP

2 tanks were installed this week on Oregon Road, work should continue on Oregon next week. Office staff have acquired 522 easements (68%) to date.

Community

Contractor installed about 700 lf of pipe on Maryland and South Carolina Roads by the HDD and open cut method. The Contractor will continue on Oregon Road next week and also start installing service lateral’s on Touhey Road. The service lateral is the small 1″ line that extends from the community main to the edge of your property. The pump inside your new tank will tie into this line. If you have any questions contact the SKI office (443-262-4675).

Transmission

Contractor installed about 800 lf of pipe at the Matapeake school site by open cut method. They will continue at this site next week.