STEP
Contractor installed 5 tanks this week on Oregon Road. County staff acquired another 14 easements to bring the total to 533 to date which is about 69% of all easements. Contractor will continue to install tanks on South Carolina next week.
Community
Contractor installed about 1300lf of pipe by the open-cut and HDD method on Oregon, Maryland, Elm, and Virginia Roads this week. The Contractor also started some road patching this week.
Transmission
Contractor installed about 700lf of pipe by the open-cut method by the Matapeake School complex. They will be tying in the open cut pipe to the pipe that was HDD a few week ago. The contractor will continue North with the tie-ins and cross Rt 8 one more time within the next few weeks.