STEP
Contractor installed 6 tanks for the week on South Carolina Road; tank installation will continue next week on Tennessee Road. We should break 100 tanks being installed sometime next week. County staff held pre-construction meetings and acquired more easements. The current easement total is 536 or 69%.
Community
Contractor installed about 2500 lf of pipe by the open-cut and HDD method on Oregon, Virginia, and South Carolina Roads this week; work will continue on Oregon Road next week.
Transmission
Contractor installed about 200 lf of pipe by the open-cut method. This pipe connected the two previously installed drilled shots of about 3000 lf from Bay City Road to North of Blunt Marsh Road.