Project Update 02.16.18

STEP Contractor installed service lines from previously installed tanks to the street on Margaret Drive. The Contractor, Community Roads Association and the County have been working in a joint venture to make the private roads more passable. County staff have acquired 661 easements to…

Project Update 02.09.18

STEP Contractor set one tank this week on Worcester Road. They also started drilling service connections on Margaret Road. They will continue on Margaret Road next week. Community Contractor installed service connection on Ackerman Road. Will continue to finish up on Ackerman next week.  Transmission…

Project Update 02.02.18

STEP The contractor installed 12 tanks for the month and ran 450lf of 1” service line to several houses on Touhey Drive. This brings the total contract completed to about 27% with about 29% of the contract time used. County staff has acquired 654…