STEP The contractor installed 3 tanks for the week. Wet conditions have slowed the tank installs; it has made the restoration efforts rough. On properties that the tank installs are still rough graded, please be patient, the contractor will restore your property correctly. Tank… Continue Reading “Project Update 01.26.18”
STEP The contractor installed 3 tanks on St Mary’s and Utah roads. They also installed 154lf of 1” service lines to tanks previously installed on Touhey Road. County staff have acquired 649 easements to date and have performed 261 pre-construction meetings with homeowners. The… Continue Reading “Project Update 01.12.18”
The contractors were only able to work one day this week due to holiday schedule and inclement weather. STEP… Next week, weather permitting, they will install tanks on Utah and St. Mary’s and continue direction drilling service lines on Touhey. Community Continue service laterals… Continue Reading “Project Update 01.05.18”
STEP Contractor installed 14 tanks for the month of December. That makes a total of 208 tanks installed to date. The contractor also started installing the 1” service line from the street to some of the previously installed tanks on Touhey drive. County staff… Continue Reading “SKI Project Report- December”