Project Update 12.21.17

Please be advised that there will be no work on the Southern Kent Island sewer project from the end of the day on 12/22/17 thru 1/02/2018. County staff will be on site, if you have any questions, on 12/26-27-28-29/2017 and again with a full…

Project Update 12.15.17

STEP Contractor installed 6 tanks for the week on South Carolina. They plan to set tanks on Tennessee and North Lake next week. The contractor will also start installing service line pipe from the previously installed tanks to the street, next week on Touhey,…

Project Update 12.11.17

STEP 6 tanks were placed this week on Virginia Road; contractor will continue installing tanks on South Carolina next week. County staff have performed 258 pre-construction meetings with homeowners, and have acquired 640 (82%) easements to date. Community Contractor installed about 130lf of pipe…

SKI Project Report- November 2017

STEP Contractor installed 25 tanks for the month on Virginia, Elm, and North Lake Roads; installation will continue on these roads next week. To date the contractor has installed 194 tanks, about 26% of the total contract and they have used about 25% of…