Month: November 2017

Project Update 11.17.17

STEP Contractor installed 6 tanks for the week on North Lake Road. They plan to continue with tank installs on Virginia Road next week. County staff has performed 242 pre-construction meetings with homeowners and have acquired 629 easements to date.   Community Contractor installed…

Project Update 11.10.2017

Step Contractor installed 5 tanks for the week on Virginia and Bay Drive. County staff has acquired 622 easements to date and has held 236 pre-construction meetings with homeowners. The contractor will continue installing tanks on North Lake, Elm, and Virginia next week. The…

Project Update 11.03.17

STEP Contractor installed 5 tanks for the week on Utah Road totaling 173 Tanks set to date.  Contractor will continue on Virginia and Bay Roads next week.  County staff have acquired 80% (616) of 775 easements required . County staff has conducted 230 pre-construction meetings…