STEP

Contractor installed 5 tanks for the week on Utah Road totaling 173 Tanks set to date.  Contractor will continue on Virginia and Bay Roads next week.  County staff have acquired 80% (616) of 775 easements required . County staff has conducted 230 pre-construction meetings throughout the community.

Community

Contractor installed 400lf and is continuing to install clean-outs and make connections between open-cut pipe sections and directional drill sections on Utah and Elm.  Next week contractor will cross Utah Road and complete tie in’s on North Lake. 

Transmission

The transmission crew installed 518′ of 14″ PVC pipe from the south side of the Porter Farm to south of Craney Creek Rd. They will continue heading south next week.

 