Project Update 10.27.17

STEP

Contractor installed 9 tanks for the week on Utah Road, contractor will continue on Utah next week. County staff has acquired 603 easements and have conducted 221 pre-construction meetings to date.

Community

Contractor installed 233 lf and is continuing to install clean-outs and make connections between open-cut pipe sections and directional drill sections on Virginia, South Carolina and Beach. Next week contractor will complete North Lake and move to Utah Road.

Transmission

Contractor installed 617 feet of 14″ pipe South of Porter Farm towards Elks Property.