Project Update 10.27.17

STEP Contractor installed 9 tanks for the week on Utah Road, contractor will continue on Utah next week. County staff has acquired 603 easements and have conducted 221 pre-construction meetings to date. Community Contractor installed 233 lf and is continuing to install clean-outs and…